On the afternoon of June 30, 2022, along with the on-site order to "close and connect to the grid", the first batch of photovoltaic power generation units of the 100MW multi-energy complementary power generation project in Yuanqu County were successfully connected to the grid for power generation. It is expected to achieve full capacity grid-connected power generation in September this year.
The 100MW multi-energy complementary photovoltaic power generation project in Yuanqu County is jointly constructed by Shanxi Widun New Energy Co., Ltd. and Shanghai Energy Technology Development Co., Ltd. It is located in Gaoluo Township, Yuanqu County, covering an area of about 3,000 mu, with a total investment of about 390 million yuan. The planned installed capacity is 100MW. After the project is put into operation, the annual power generation is about 138 million kWh. It is expected to save 42,000 tons of standard coal and 101,000 tons of carbon dioxide emissions each year, which can effectively reduce the consumption of coal resources.
According to the spirit of the 2021 document issued by the Shanxi Provincial Energy Administration, this project is required to be connected to the grid for power generation on June 30, 2022. However, due to factors such as repeated epidemics, the time can be extended to September 30, 2022. In the face of multiple difficulties, the Yuanqu County Party Committee, the county government and the project team worked together to rush the construction period and schedule.
On the government side, set up a special work class, mobilize capable forces, take the initiative to serve in the front, improve service efficiency, ensure "zero interference" and "barrier-free" project construction, and provide a "green runway" for grid-connected power generation. In terms of engineering, all the construction personnel have always been anchored in the "630" goal, formulating detailed plans, focusing on key links such as on-site construction safety management, large-scale transportation, etc., and speeding up various tasks on the premise of ensuring safety and quality Solve and coordinate various problems encountered on site, overcome the difficulties together, and finally successfully achieve the "630" grid-connected power generation goal.
In the follow-up, the project team will fully devote itself to the project trial operation guarantee work, make new contributions to the guarantee of clean energy, promote the realization of the "dual carbon" goal, and add green to Yuanqu County's all-round promotion of high-quality sustainable development. New kinetic energy.